Development And Upgrading Of The Proposed Pan Borneo Highway In The State Of Sarawak, Malaysia – Phase 1

Contract Sum (MYR)

RM1,460,773,150.55

Commencement/Completion

March 2016 / March 2020

[Contract No. PDP/PBHS/SPJ/2016/WPC-03
(Serian Roundabout To Pantu Junction)]

Contract Duration   : 48 Months

This project was awarded to Zeon Kimlun Consortium Sdn Bhd March 2016 with a contract sum of RM1.46 billion. The Project involves the development and upgrading of the proposed Pan Borneo Highway start from Serian Roundabount to Pantu Junction which approximately 75km, it covers the works for the upgrading the existing road from Serian Roundabout to Pantu Junction. The Project is estimated to be fully completed in March 2020.