Contract Sum (MYR)

29,900,000

Commencement/Completion

1993/1996

simpang_tiga_flyover
Scope of work:

  • Survey and clearance of project site including removal of existing vegetation and obstructions
  • Execution of earthworks for cuttings and embankments
  • Construction of pavements
  • Execution of piling works to structures, embankments and drains
  • Supply and installation of street lightings
  • Diversion of affected utilities including water, electricity and telecommunications
  • Provision of temporary road diversions
  • Development of all major and minor road junctions
  • Provision of road accessories