Repair & Maintenance of Access Roads And Slop Stabilisation Works With ROW of Sabah Sarawak Gas Pipeline, Package E
Contract Sum (MYR)
RM31,530,000
Commencement/Completion
2015 / 2018
The Scope of Works is as follows:
a) Slope Stabilization Works which include the following works:
- Soil Investigation & Survey Works.
- Prepare detail design & drawing for slope protection.
- Slope Protection Works (Construction)
- Engineering firm Supervision, testing & certification.
- Instrumentation Works
- Preparation and Submission of As-built drawings
b) Other Civil & Structure Works within the ROW of Sabah Sarawak Gas Pipeline based on work orders issued by Petronas Carigali Sdn Bhd